Why the first fix decides how well your kitchen works
Before a single tile goes on a wall or a cabinet gets hung, your kitchen's plumbing and electrical services have to be in the right place. This stage — the first fix — is when pipework and cabling are run through floors, walls and ceilings while everything is still open and easy to reach. In Chorley and across Lancashire, where we work in everything from Victorian terraces with solid stone walls to converted barns near the West Pennine Moors and newer estates in Buckshaw Village, this is the stage that most often makes or breaks a kitchen budget.
Once the plasterboard and skim coat go on, shifting a waste pipe or adding a socket means chasing walls, patching plaster and repainting. It's messy, costly and completely unnecessary. A couple of evenings spent planning now will save you weeks of frustration later.
Plan the layout before the pipework
Everything follows the layout: the sink, the hob, the fridge, the oven. Work out your appliance sizes from the actual specification sheets, not from memory or old assumptions. A 600mm wide dishwasher is not always 600mm deep, and American-style fridge freezers often need more clearance at the back than the manufacturer's brochure suggests.
Keep the classic working triangle in mind — sink, hob and fridge within easy reach of each other — but be realistic about the shape of your room. If you have a long, narrow kitchen with a chimney breast, the boiler in one corner and a back door in another, you may need to compromise. Be honest about the compromises before the plumber picks up a drill.
Plumbing first fix: water in, water out
The important decisions here are about where water arrives and where it leaves.
- Hot and cold feeds: Plan separate runs of 15mm pipe to the sink, dishwasher and any appliance that needs a supply. Instant boiling-water taps need a cold feed only, but they also need a nearby socket and a route for the waste.
- Waste routes: Gravity is not negotiable. A sink waste needs a sensible fall to the outside drain, and a washing machine or dishwasher needs a standpipe or spigot with a trap. If you are moving the sink across the room, check whether you can get the waste through the floor joists or whether you will need a pumped solution.
- Isolation valves: Have one fitted on every feed. It's a small cost and it means you can swap a tap or a washing machine without draining down the whole house.
- Stopcock and pressure: Check you have decent water pressure before choosing a rainfall shower head or a high-flow boiling tap. In older Lancashire properties with lead or narrow-bore pipework, this is worth testing first.
Lancashire's water is moderately hard in many areas, so if you're considering a water softener or a filtered tap, the plumbing needs to be planned in now — not squeezed in behind a cabinet later.
Electrical first fix: circuits, sockets and lighting
Electrical work in a kitchen is notifiable in England and must meet the current wiring regulations, so use a registered electrician and get the certificate at the end.
- Dedicated circuits: Induction hobs, double ovens and combi microwaves usually need their own circuit. Check the rating on the appliance data sheet before your electrician orders cable.
- Sockets above the worktop: Position them where you will actually use them — near the kettle, the toaster, the coffee machine. Keep them clear of the sink and hob, and consider that a splashback of glass or tile may change how they sit.
- Sockets below the worktop: Dishwashers, washing machines, waste disposals and boiling taps all need a supply. Put these on an easily accessible adjacent unit or a switched spur above the worktop, so you are not dragging a machine out to isolate it.
- Fridge and freezer: Ideally on a circuit that lets you isolate them separately if you go away, and always on a socket you can reach.
- Lighting: Plan layers — general ceiling lighting, task lighting under wall cabinets, and perhaps a pendant over a breakfast bar. Under-cabinet LEDs need their driver accessible and their cable routed before the cabinets are fitted.
- Extraction: A ducted cooker hood needs a route through an external wall with a 100mm duct. If you cannot get outside, a recirculating hood is an option, but it will never perform as well.
Coordinating plumbers, electricians and the kitchen fitter
The most common cause of a delayed kitchen is trades waiting on each other. Sort the sequence early:
- Strip out the old kitchen and confirm the layout.
- First fix plumbing and electrical — ideally in the same week, so cables and pipes are not fighting for the same route.
- Building control or electrical sign-off of the first-fix work if required.
- Plastering and drying time.
- Second fix: units, worktops, appliances, final connections, testing and certification.
Keep all of your pipes and cables in defined zones — usually horizontally between 150mm and 450mm from the floor and vertically rising from each outlet. That way, when you or a future owner drills into a wall to fit a cabinet or shelf, you know where not to go.
Before the plaster goes on: your last chance checklist
Ask yourself these questions while the walls are still open. Take photos of every wall, floor and ceiling before they close up — you will be glad of them in five years' time.
- Are all appliance sizes confirmed and cross-checked against the plan?
- Is the boiler flue route clear and the condensate pipe run correctly?
- Does every socket, light and switch end up where you actually want it?
- Is the extractor ducted outside, not just venting into a void?
- Are isolating valves fitted and labelled?
- Have you photographed and measured every pipe and cable run?
Get this stage right and the rest of the renovation becomes a sequence of satisfying steps rather than a series of expensive surprises. In a county full of solid walls, tricky chimney breasts and period quirks, careful first-fix planning is the difference between a kitchen that merely looks good and one that genuinely works every day.